U.S. data center construction costs rose 13% over the past year, driven by an unprecedented surge in demand for artificial intelligence computing power that has far outstripped the supply of powered land and skilled labor. A new global report shows that this price growth is more than double the global rate and roughly triple the ten-year average for the industry.
At the same time, individual energy infrastructure projects tied to these massive tech hubs are seeing dramatic cost overruns. For instance, a natural gas plant being built by Entergy Louisiana to power Meta's massive data center in Richland Parish has seen its projected price tag jump by 63% to $1.755 billion.
What happened
The 13% spike in construction costs stems from a report by Turner & Townsend, which examined over 500 live or recently completed projects across 62 global markets alongside a survey of 400 industry experts. While cost inflation showed some stabilization, it was vastly overshadowed by the aggressive speed required to deliver new facilities. Paul Barry, North America data center lead for Turner & Townsend, noted that aggressive schedules force contractors and subcontractors to bake substantial risk allowances into their pricing, covering things like overtime, labor attraction, and the financial risk of accelerated delivery.
Power availability remains a primary bottleneck. Over half of the survey respondents globally cited power as a major obstacle to delivery, noting that utility connections routinely take one to two years, and nearly a third reported wait times exceeding two years. Regional power costs vary starkly, ranging from $15.01 per watt in Silicon Valley to $10.51 per watt in Dallas for a standard 60-megawatt design. Furthermore, only a quarter of respondents reported that their contractor capacity to manage backlogs was sufficient.
In Louisiana, local energy projects face their own acute cost pressures. Entergy Louisiana's Waterford 5 gas plant—one of three gas plants being built to serve Meta's $50 billion Hyperion data center—saw its cost estimate climb $676 million higher than originally projected. Earlier filings cited complex geotechnical conditions requiring specialized pile foundations, site development work, and higher labor and equipment expenses.
Why it matters
The soaring cost of building and powering digital infrastructure has immense financial implications for the technology, real estate, and utility sectors. Capital expenditure on global data centers is projected to skyrocket from about $800 billion to $1.8 trillion per year by 2050, with the United States capturing roughly half of all global investment in artificial intelligence infrastructure. For local utility customers and state regulators, the rapid expansion brings intense debate over who absorbs these multi-billion-dollar expenses. In Louisiana, Entergy is expected to seek regulatory approval for seven additional gas plants and transmission lines using a fast-track directive that waives traditional rules meant to protect ratepayers from high costs.
The background
Data centers are specialized physical facilities housing the powerful computers and networking equipment that run cloud computing and modern artificial intelligence applications. The explosive growth of generative artificial intelligence has triggered a historic land and energy rush by major technology companies to secure massive amounts of electricity and computing capacity. In Louisiana, state officials including the governor signed non-disclosure agreements during early negotiations involving a shell company named Laidley LLC, which Meta used before the Louisiana Public Service Commission ultimately approved the power plant project in August 2025.
What happens next
Industry experts project that cost increases will moderate slightly to a range of 6% to 10% over the coming year as many major projects enter their execution phases and contractual risks are already baked in. However, the continuation of these cost trends depends heavily on whether the current hyper-demand for artificial intelligence infrastructure persists. In Louisiana, state regulators are poised to review Entergy's upcoming applications for seven additional gas plants and related transmission lines, testing the boundaries of fast-tracked utility approvals.
Key takeaways
- U.S. data center construction costs surged 13% year-over-year, driven by intense demand for artificial intelligence computing power.
- Power availability remains a severe bottleneck globally, with utility connections taking anywhere from one to more than two years.
- Entergy Louisiana's gas plant project intended to power Meta's data center saw its budget swell by 63% to $1.755 billion.
- Global capital expenditure on data centers is projected to climb from approximately $800 billion this year to $1.8 trillion annually by 2050.